Projects >
Crystal Springs-San Andreas Transmission Upgrade
Project Date: 2011 - Active Project
Heavy underwater construction involving "Cast in Place Underwater Concrete", Underwater Pipe Installation, Grouting and installation of structural steel and fish screens.
This two year project seeks to improve seismic and delivery reliability of this transmission system. The proposed project area (including all construction, staging, and access areas) covers approximately 135 acres and is composed of seven distinct project components running approximately 7.6 miles across the Peninsula Watershed. Ballard Diving and Salvage is a second tier subcontractor providing diving, remote operated vehicles and marine construction support to the project.
 |
|
| SFPUC Awards $99.7 Million Construction Contract for Crystal Springs |
|
 |
|
|
|
|
|
| |
|